Pre-Upgrade Tasks
2-12 Express5800/320Fc: Active Upgrade™ User’s Guide
To set the enclosure with A-side power as primary.
1 Open the ft Server utility.
2. Expand FTServer
3. Expand CPU Module
4. Expand CPU Module (ID:1)
5. Under BringUp/BringDown, click the Down button.
6. Click Ok in the Confirmation box.
7. Click Ok in the Information box.
8. Skip steps 9-13 if the Power Switch is illuminated on the CPU/IO module 0.
9. Expand PCI Module.
10. Expand PCI Module (ID:1).
11. Under BringUp/BringDown, click the Down button.
12. Click Ok in the Confirmation box.
13. Click Ok in the Information box.
14. Expand PCI Module (ID:1).
15. Verify that the current status is removed.
16. Under BringUp/BringDown, click the Down button.
17. Click Ok in the Confirmation box.
18. Click Ok in the Information box.
19. Skip steps 20-24 if the Power Switch is illuminated on the CPU/IO module 0.
20. Expand PCI Module (ID:11).
21. Verify that the current status is removed.
22. Under BringUp/BringDown, click the Down button.
23. Click Ok in the Confirmation box.
24. Click Ok in the Information box.
N O T E
After this procedure, you might need to wait 5-10 minutes
for the system components to stabilize and return to full
duplex mode before running a readiness check.
Related Topics
“Pre-Upgrade Tasks” on page 2-7
Configuring the Active Upgrade Process
Vista de pagina 33
1 2 ... 29 30 31 32 33 34 35 36 37 38 39 ... 119 120

Comentarios a estos manuales

Sin comentarios